The Badrah Phase 1 project is more than 60% complete.
Overall structural works for the townhouses are finished. The internal trades are underway and are now progressing hand-in-hand with MEP. The external works have also commenced, including water tanks, pergolas and facade works.
The apartments superstructure works are in progress with some buildings reaching 3rd floor concrete slab. Furthermore, the internal trades are scheduled to start in the coming months.
Nakheel.com